Last update: 08 February 2008

Project questions or comments?  Please email David Harlow

 Home

 About the Project

 Project Diary

 Photo Galleries

 Map

 A4 Handout

 Fisheries News

 Contact

Project Diary

The diary follows project progress (latest news comes top)

Total volume delivered by Oranje: 1,020,456 m3

Total volume measured on the beach: 897,722 m3

About the difference between the two totals

January 2007

23rd
Load #81, the last of the project, was pumped ashore today at Alum Chine.

The Oranje has left for Rotterdam; work now starts to dismantle the pipeline along the beach.

22nd
Project Managers confirm the final load is scheduled to be pumped ashore tomorrow (Tuesday) at about 10.00 a.m.
21st
Load #77 was pumped ashore this afternoon, watched from the promenade by a large crowd enjoying the January sunshine.

2km of beach has now been replenished to the west of the sinkerline, reaching Middle Chine, with works nearing completion.  Weather permitting, the last load should be delivered to the shore on Tuesday.

19th
Work resumed yesterday evening when the storm had passed.  Load #72 was pumped ashore early this morning, completing the beach at Durley Chine.  Some 1,788m of shoreline now replenished to the west of the sinkerline.  Total sand pumped ashore 765,00m3.
17th
After delivering load #69 at Durley Chine this afternoon the Oranje left for bunkering in the Solent.  She is due to return with the next load late tonight or early tomorrow morning - weather dependent.  Storm force winds forecast overnight.
16th
Members of the Institution of Civil Engineers (ICE) visited the project today; presentations and lunch at the Royal Bath Hotel were followed by a site visit to Durley Chine.  A planned trip out to sea for a close-up view of the Oranje approaching and linking to the sinkerline had to be cancelled due to poor weather.

Loads #67 & 68 pumped ashore.  It is estimated that there are just 14 more loads required to complete the project (7-8 days work).

14th
Crowds gathered on a mild & sunny Sunday to watch work as it progresses towards Durley Chine.
11th
Pipework beneath Bournemouth Pier is complete but there are some engine problems for the Oranje; repairs take place at a sheltered location. 

Delays due to the poor weather lead the project team to revise the anticipated date of completion to 24th January.

9th
The last load for the eastern end of the project was completed at midnight last night bringing the total quantity of sand delivered to the coast to date to 625,000m3 [more].  The onshore pipeline is now being dismantled.

Meantime, load #52 was pumped from the sinkerline position to the west (toward Bournemouth Pier) between groyne Nos. 12 & 13.

It is anticipated that work will reach Bournemouth Pier by Tuesday afternoon, the 9th.  As pipework goes on beneath the pier the Oranje will leave for minor repairs and should return to continue pumping on Thursday.

6th
Load #47 pumped ashore at noon today between groyne Nos. 28-29.  Just three more loads needed to complete work on this section of beach.
5th
2,600m of beach has now been replenished with about 600,000m3 of material, and work towards Southbourne should be completed tomorrow.

If all goes to plan, replenishment will continue with sand being pumped west of the sinkerline between the Piers on Monday, 8th January.

2nd
The Oranje spent Sunday night in Poole Harbour so that the crew could enjoy the New Year celebrations at Poole Quay, but they were back to work the following day.

Load #38 delivered this morning completes more than 2km of beach using 475,000m3 of sand.  Recent bad weather has delayed the project but only slightly and the revised target is to reach Portman Ravine Zigzag on 5th January.

December 2006

29th
Load #32 took us up to groyne No 24 today - one groyne beyond Boscombe Pier - after which the Oranje went to refuel at Southampton.  She is due back tomorrow morning.
27th

Load #30 was delivered to the beach east of Boscombe Pier this morning.  Some 1,700m of beach has now been replenished using approx. 315,000m3 of material [more].

The aim is to reach the easternmost point of BIS4.2 (Portman Ravine Zigzag) by 4th January; the operation will then return to the sinkerline between the two Piers and start pumping westwards towards the Borough boundary with Poole.

23rd
Load #22 arrived at the beach at 11:00 today between groyne Nos. 20 & 21.  Approximately 1,050m of beach has now been completed and the aim is to reach Boscombe Pier by Christmas Day.
20th
Load #16 at 05:40 completed work to groyne No. 18.  The dredger is due back at about 16:00 hours.
19th
Load #13 was pumped on to the beach between 07:30 and 09:30 today between groyne Nos. 17 & 18.  It is taking 2-3 loads to fill a groyne bay, and each bay represents approximately 150m of beach.
15th
Load #4 delivered at 07:15.  Some 150m (approx) of beach has now been replenished between groyne Nos. 14 & 15.  Each hopper load delivers 11,500-13,000 m3 of sand and takes 2-3 hours to offload.
14th
Valves and a 'T' piece have been fitted to the end of the sinkerline to allow sand to be pumped both east and westwards from its position at East Cliff.

The second load of sand was pumped (east) between 06:00 and 09:00 this morning and #3 at 18:48; an early morning & early evening visit by Oranje is likely to be the routine for the next few days at least. 

13th
The Oranje arrived at 17:30 this evening with a full hopper; the first load of sand was pumped on to the beach from 18:00.
12th
The Oranje is expected to arrive at Bournemouth tomorrow between 14:00 and 16:00.  A section of onshore pipeline has been added to the sinkerline today, preparing for her arrival.
9th
The 1,150m sinkerline is at Bournemouth, brought ashore at about 13:35 at the bottom of the East Cliff lift [pictures in the photo galleries].  It has been sunk to the seabed and awaits the arrival of the Oranje.
5th
The project management team visited Harwich, to brief the dredger Oranje's Captain about the Bournemouth Project. Oranje is now expected to arrive at about midday on Wednesday 13th December, when her work at Harwich is complete.

At Poole, the sinkerline is due to be completed over the next couple of days, and will be moved offshore on Saturday the 9th (weather permitting) to its position between Bournemouth & Boscombe Piers.

4th
The weekend's gales caused a considerable amount of overtopping and damage between Bournemouth and Boscombe Piers, where the beach is low and awaiting replenishment.  Large quantities of sand, gravel, seaweed and debris were thrown onto the promenade. 

By contrast, the newly replenished beaches at Southbourne stood up to the storm very well, with a further slight increase in crest level, and no water or debris reaching the promenade.

November

29th
1,050m of sinkerline now complete, 100m to go.  Completion still on course for Friday 1st December, with the dredger due to arrive on the 11th.
24th
Work on the sinkerline has progressed to 'No Mans Land', just east of Canford Cliffs Chine.  The crew expect to have completed it by 1st December.
20th
The crane has left site and parking restrictions at Branksome Chine have been lifted.  Work on the sinkerline continues along the beach at Poole.
17th
The appalling weather this morning put a temporary halt to operations; it was too windy for the crane to operate safely.  Things improved this afternoon and we anticipate we will finish off-loading tomorrow morning.
16th
Sand levelling plant has arrived, and work has started on welding sections of sinkerline.  More pictures at the photo galleries.
15th
First deliveries - sections of pipe for the sinkerline - are offloaded from midday.
14th

The ship carrying lengths of pipeline has arrived in Poole Harbour and is being off-loaded.  Meanwhile the crane awaits deliveries at Branksome Chine car park.

 

23.01.07 - the Oranje leaves Poole Bay bound for Rotterdam

22.01.07 - heading for Alum Chine and project's end

19.01.07 - work resumes after the storm

18.01.07 - storm force winds gusting to 63 mph

16.01.07 - members of the Institution of Civil Engineers visit the project

14.01.07 - a sunny Sunday, east of Durley Chine

12.01.07 - work continues west of Bournemouth Pier

Daily Echo 03 January 2007 (click on image to enlarge in new window)

27.12.06 - work continues east of Boscombe Pier

20.12.06 - dredger in the mist

15.12.06 - the first stretch of replenished beach BIS4.2

12.12.06 - a section of onshore pipeline is secured to the sinkerline

09.12.06 - the sinkerline is brought ashore at Bournemouth

29.11.06 - the sinkerline stretches from Branksome Chine to Flaghead Chine

16.11.06 - Sections of sinkerline laid out for fabricating

15.11.06 - Sections of sinkerline delivered first to Branksome Chine cark

14.11.06 - Pipe sections arrive by sea

   

• Home • About the Project • Project Diary • Photo Galleries • Map • A4 Handout • Fisheries News • Contact •

This product includes mapping data licences from Ordnance Survey © Crown Copyright and/or database right 2006 License Number 100024248

  © 2005-08 Borough of Poole Leisure Services & partners

Re web content or photos contact: Sarah Austin