Overall
length |
97.7m |
Moulded
depth |
7m |
Hopper
capacity |
4,900m3 |
Dredging
depth |
28m
(max) |
Speed
(loaded) |
13.2
knots |
TSHD
Waterway arrived in Poole on the 15th December, when the Volvox
Scaldia was demobilized.
Overall
length |
94.5m |
Moulded
depth |
6.3m |
Hopper
capacity |
3,510m3 |
Dredging
depth |
29.6m
(max) |
Speed
(loaded) |
11.5
knots |
TSHD
HAM 311 and Waterway will be working together
to replenish Poole's beaches.
Overall
length |
85.8m |
Moulded depth |
6.3m |
Hopper
capacity |
2,548m3 |
Dredging
depth |
28m
(max) |
Speed
(loaded) |
11.2
knots |
The
Volvox Scaldia was used to replenish Swanage beach.
Beach
work (moving and levelling the sand pumped ashore) has been sub-contracted to Ovenden
Civil Engineering
A
pipeline (sinkerline) approximately 750m long x 700mm diameter is
floated into position and then sunk to the seabed during replenishment
work.
At
the seaward end the sinkerline is coupled to a 36m flexible riser pipe
section, followed by a 100m flexible floating pipeline. With
assistance from the multicat, the dredger couples to the floating
pipeline via a bespoke coupling ball-joint system.
At
the landward end the sinkerline is fitted with a steel flange
from which sections of shoreline pipe (approximately 12m long) can be
coupled to discharge sand to the required locations. Y-pieces with
valves can be introduced to the pipeline to direct the loads to
different areas of the beach.
Sand
bunds are pushed both toward the seawall (for protection) and towards
the shoreline to retain the new sand on the beach and avoid losses to
the foreshore. The sand/water mixture from the pipeline flows in
between these bunds where it settles on the beach, with the water
returning to sea.
Measuring
quantities pumped ashore
There
are two factors to take into account when estimating the quantity of
sand reaching the beach. The amount we claim as pumped ashore
is recorded by the dredger and we have to allow for a "bulking factor"
of 1.2 due to the material being mixed with water in the hopper.
For instance, if we're told that 3,000 cu.m. has been pumped from the
hopper it would equate to 2,500 cu.m. actual material dredged.
We then allow for an
estimated 20% of that 2,500 cu.m. being lost to the foreshore during
pumping, so only 2,000 cu.m. might be left on the
beach.
These figures provide guidelines. Beaches are
independently surveyed on a daily basis, comparing levels and widths to
a baseline survey carried out before work commenced, and in that way we
get a far more accurate idea of how much sand has actually been
delivered.
During the project Van
Oord ran trials for a newly developed method of monitoring flow & volume
through the pipeline.
 |