CURRENT PROJECTS

Poole Quay Sea Wall / Dolphin Haven 2015-2019

A project to safeguard the integrity of the town’s quay structures whilst enabling the Environment Agency to address the requirements to improve its flood defences.

LEAD AUTHORITY

Poole Harbour Commissioners

WORKING WITH

Environment Agency

START DATE

March 2015

END DATE

Summer 2019

LATEST UPDATE

4th June 2019

Showing the difference in levels once Phase 1 of the works were completed, and before Phase 2 of quay level raising had begun.

Project Overview

This three-phase project will join up the existing sea defence schemes to a consistent defence level with adjacent schemes. It will address a low area of flood defence protection between adjacent flood defence schemes that have been carried out previously in the Old Town area and Green Gardens (by the Old RNLI Lifeboat Station).

The objectives in summary:

  • Renew the quay wall over a length of 375m between a point opposite Hennings Wharf and the existing flood defence wall adjacent to the slipway alongside the Old Lifeboat Station.
  • Improve the level of flood defence to a consistent 2.35m AOD.
  • Deliver any necessary finishes, surface level adjustments, drainage and paving to meet the requirements of the Local Planning Authority.
  • To maintain the agreed works.

Project Progress

  • Phase 3 works to raise the quay-side level started in April 2019 and are due to be completed by summer 2019.
  • Phase 2 works were completed in April 2017.
  • Phase 1 works at Fisherman’s quay were completed in July 2015 as Permitted Development.

Phase 3

Raising the level of Poole Quay from the area by the landing pontoon bridge westwards to connect with the existing flood defences at the roundabout

Flood defences at the roundabout

Phase 1-2 photos

Project background

Poole Quay sea wall is owned and operated by Poole Harbour Commissioners (PHC). It is built of a mixed construction. Many sections were reinforced with steel sheet piles in the early 1980s, but the length of quay East of Dolphin Quays to the Old Lifeboat station remains a much older masonry construction.

A divers’ survey from 2012 conducted by PHC shows that the total length of the masonry wall of the east quay is in very poor condition with voids behind.  It had timber fender piles and rubbing strips missing.  These protect the wall and boats from being damaged.

The quay provides defence against flooding to the area of Old Town behind the quay wall where land levels are significantly lower than the flood defence level. Therefore if the quay was overtopped by seawater to any extent there would be flooding in that area.

Before it was raised the quay wall provided a 1 in 200 year standard of protection until 2020. In order to provide flood protection through to 2060 the defences on the quay needed:

  • to be renewed. The sea wall, over a length of 375m, between a point opposite Hennings Wharf and the existing flood defence wall adjacent to the slipway alongside the Old Lifeboat Station.
  • to be improved. The level of flood defence needed to be raised by about 350mm to a consistent level of +2.35m AOD (Above Ordnance Datum).
  • to deliver any necessary finishes, surface level adjustments, drainage and paving to meet the requirements of the Local Planning Authority.
  • to be maintained.

The scope of these works has involved:

  1. new steel sheet piled walls;
  2. concrete parapet walls;
  3. raised surfacing & associated drainage works as well as maintenance / repair works to existing sheet piled walls;
  4. replacement of fender timbers.

Overall scheme completion is due by summer 2019.