CURRENT PROJECTS

Cliff Monitoring and Stabilisation Works

Canford Cliffs, 2017-2020

Phase 2 of works to address the landslip at Canford Cliffs in February 2017 involves a 12-month programme of stabilisation works.

LEAD AUTHORITY

BCP Council

START DATE

March 2019

LAST UPDATED

14th January 2020

The 2017 landslip at Canford Cliffs

The 2017 landslip at Canford Cliffs

Project Overview

In February 2017, at Canford Cliffs, a section of cliff approximately 10m wide x 0.5m deep eroded and slipped, resulting in the closure of two blocks of beach huts directly below it and postponement of a planned investment in seafront infrastructure.

Following completion of the 2017-2019 cliff face monitoring project (full details below) the Council agreed a 12-month programme of stabilisation works at a cost of approximately £3.1 million.

Cliff Stability update 3rd January 2020

There was a further cliff slip over the Christmas period, and in recent days there has been significant movement to the east of the original cliff slip. This increases the risk that material could pile up at the back of the beach huts which may be of sufficient force to damage them or cause a partial collapse. For this reason a safety zone has been constructed in this area; warning notices are on site in the area. Assessments are due to take place on 15th January.

If you are a beach hut tenant in the safety zone and need access to your hut, please contact Customer Services on 01202 708181.

Vegetation clearance January 2020

We have been cutting back vegetation to enable structural engineers to assess the condition of the cliff face and monitor its stability. From 6th January, we will continue to clear vegetation extending eastwards towards and beyond the zig-zag footway. This will help make the final preparations for engineering works to stabilise the cliff.

By cutting the vegetation close to ground level we can complete wildlife surveys to ensure all protected reptiles and nesting birds are excluded from the proposed working area. Reptiles are being moved to a prepared ‘friendly’ habitat outside of the exclusion zone and once the stabilisation works have been completed they will be able to colonise the whole area again.

Borehole Drilling, April 2019

On the promenade and beach hut terraces around block numbers 1–11 (borehole location map, pdf). This further ground investigation is required to provide the necessary information to complete the designs for cliff stabilisation, the new beach hut foundations and the retaining wall located behind the beach huts.

Protecting Wildlife

The area of cliff affected by the landslip is part of the Poole Cliffs SNCI (Site of Nature Conservation Interest) which is managed by the Council for it’s nature conservation interest. It provides an ideal habitat for the nationally rare Sand Lizard and Dartford Warbler which are both protected species, and other birds that might be nesting in the gorse bushes.

During the period of cliff stability monitoring it was necessary to clear cliff vegetation to enable structural engineers to assess the condition of the cliff face. At the same time reptiles were encouraged to gradually move away from the ‘exclusion zone’ to pre-prepared reptile-friendly habitats beyond it. Surveys were carried out until winter hibernation to ensure the zone was clear of reptiles in anticipation of cliff stabilisation works.

The Council’s biodiversity officer has been working, and continues to work throughout this project to protect both habitats and wildlife.

Monitoring Cliff Stability
2017-2019

Monitoring movement of the cliff face at Canford Cliffs following the landslip in February 2017.

LEAD AUTHORITY

Borough of Poole

WORKING WITH

START DATE

24 April 2017

END DATE

05 February 2019

Monitoring Cliff Stability - Canford Cliffs 2017

Project Overview

In February 2017, at Canford Cliffs, a section of cliff eroded and slipped; it is now resting half way down the cliff face. Since the original slip more material has moved with it. There is some concern the eroded section could continue to move downwards to promenade level, especially in the event of heavy rain.

The slip, at approximately 10m wide x 0.5m deep, is large enough to warrant further investigation in order to establish how active it is, and whether there is any other movement in the area. Stabilisation measures can then be decided.

A short stretch of footpath on Cliff Drive was undermined by the slip and is temporarily closed.

The planned investment in new beach huts and seafront infrastructure, due to start in 2017, has been postponed as a result of the landslip and ongoing investigations.

Project Progress (latest first)

  • March 2019 cliff stabilisation works to go ahead. Geology reports having been reviewed and options considered, the Council has agreed a recommendation for a 12 month programme to stabilise the whole cliff face at a cost of approximately £3.1 million.

  • December 2018 we cleared more vegetation extending eastwards towards the zig-zag footway and Holm Oak (which remains), enabling structural engineers to assess the condition of the cliff face and monitor its stability. This work reveals the full extent of the required cliff stabilisation work. Spraying and vegetation clearance continued throughout the winter months to allow wildlife mitigation. By cutting the vegetation close to ground level we provide light for the reptiles, areas for nesting birds and give the native heathers a chance to re-establish.

  • During July 2018 reptile fencing was used to create an exclusion zone, preventing reptiles from moving into the potential cliff stabilisation working area; those already in the area were moved to pre-prepared ‘reptile-friendly’ habitats outside the exclusion zone. Surveys continued until winter hibernation to ensure they had all been removed.
  • 29th May 2018 Spraying cliff vegetation to allow reptile surveys; a reduction in thick vegetation will encourage protected reptiles to gradually move away from sprayed areas in preparation for the stabilisation works later in the year. Further spraying & cutting throughout the growing season as required.
  • 19th March 2018 Drilling for soil samples up to a depth of 30m, over a period of 3-4 weeks. This work is part of the continuing ground investigation to help understand the geology of the site; the information collected will help inform what cliff stabilisation works will be needed in the future.
  • 8th January 2018 Further cliff movement requires a safety zone to be set up on the promenade at the base of the area.
  • 18th September 2017 Work began to remove vegetation cover from the site; bare ground allowed engineers to gain a better understanding of the condition of the cliff face during the monitoring period. This work was carried out in two stages to give the opportunity to move any emerging protected reptiles to the reptile-friendly landscape prepared for them on either side of the cleared area.
  • 12th June 2017 We assessed the cliff stabilisation schemes that were implemented in the 1970s either side of the current slip before deciding what scheme is needed (and if we need to re-do the 70s work)
  • 4th May 2017 Channel Coastal Observatory started their monitoring.
  • 2nd May 2017 all the targets (45 in total, 3 rows of 15) are now in place.
  • 24th April 2017 work commenced on the installation of steel targets at regular intervals along and down a 300m section of cliff at Canford Cliffs. The monitoring of these targets will identify whether the cliff is moving or stable, and help establish what future cliff stabilisation works may be needed.

Once a fortnight, over an initial three month monitoring period, a laser scanner will read these targets and accurately measure their position, within a +/-2mm tolerance, to see if there is movement. The targets are needed because the laser cannot see through the vegetation to read the cliff face itself. The regional Channel Coastal Observatory will conduct the monitoring using the same laser scanner they already use to measure the level of Poole’s beaches for coast protection purposes.

June 2017: Assessing previous cliff stabilisation work

May 2017: Monitoring methods

April 2017: The slip and installing the targets

Historical cliff slips at Canford Cliffs

Over the past 40 years there have been three significant cliff slips at Canford Cliffs Chine. The first two happened during the 1970s and one of these resulted in a block of beach huts being demolished (these were only reinstated in 2014). The third significant slip took place in 1993.

Each of the slips at Canford Cliffs required stabilisation schemes including a system of transverse steel beams positioned down the cliff face and a series of soil nails to pin and hold a top section of the cliff.